Budding rare earths miner Lindian Resources has moved a step closer to production after taking stock of its mining fleet at the companyโs Kangankunde project in Malawi.
The fleet, made up of a dozer, excavators, wheel loaders, a grader, articulated dump trucks and a drill rig, forms a core pillar of the companyโs owner-operator mining model and will underpin initial mining activities, including tailings storage facility construction.
Mining fleet arriving on site at Lindian Resourcesโ Kangankunde rare earths project in Malawi.
With early works and site establishment wrapped up, Lindian says construction activity is gaining momentum across multiple fronts as it targets first production later this year.
The mobile workshop facility is on track, with earthworks complete, structural fabrication underway and key materials procured. The facility is being built to support maintenance and servicing of the Komatsu owner-operator fleet.
In other areas of the project, processing plant development remains ahead of schedule, with Lindianโs design-and-construct partner, Obsideo Consulting, set to mobilise to site next month to begin civil works, following completion of detailed engineering and construction planning.
Construction of 10 VIP accommodation units and a supporting mess hall is nearly complete with delivery due mid-month, providing dedicated housing for the Obsideo project team during execution of the processing plant civil works.
Malawiโs Chief Inspector of Explosives has given the thumbs-up to the proposed explosives magazine, with early site works and clearing in train. The facility will feature bulk explosives storage, CCTV and secure perimeter fencing.
The projectโs administrative building is taking shape, with foundations now laid, allowing construction to kick off. The facility will house management offices, technical and IT workspaces, logistics functions and a site clinic, forming the operational hub through construction and into production.
Elsewhere, work on the fuel farm is progressing well. The facility will house two 40,000-litre bulk fuel storage tanks โ a critical lifeline as the project progresses toward ramp-up and first production. On the power front, ESCOM Malawi is busy installing overhead power lines to support Kangankundeโs first-stage operations.